How Long Does It Take to Install a Concrete Pool?

The Full Process from Landscape Design to Installation with Approvals in Newcastle,NSW,Australia

Installing a concrete pool is one of the most exciting upgrades you can add to your home, especially in a city like Newcastle where outdoor living is part of the lifestyle. But one of the first questions homeowners ask is: “How long does it actually take to install a concrete pool?”

Whether you’re in Merewether, Mayfield, Wallsend, Charlestown, Kotara or Lambton, the timeline generally follows the same structure — from design to approvals and final installation.

Below is a complete breakdown of the process, step-by-step, to help you understand how much time to expect when working with professional pool builders near me in Newcastle.

 

1. Landscape Design & Personalized Planning (1 - 3 Weeks)

Your journey begins with an on-site consultation where your chosen builders pool experts analyse your space, soil, slope and overall landscape. This includes discussing shapes, depths, features, and how your new concrete pool will complement your outdoor area.

During this stage, detailed drawings, 3D designs, and engineering plans are created. This step makes sure that your concrete pool exactly fits your vision, since they can be fully customized. The design phase usually takes between 1–3 weeks, depending on revisions and approvals.

 

2. Council & Engineering Approvals ( 6-12 Weeks )

Every concrete pool in Newcastle requires council permits and engineering approvals. In places like Charlestown or Kotara, where block sizes aren't all the same, this step might take a little longer.

Pool makers handle all the paperwork, like site plans, safety paperwork, and structural engineering. The time it takes to get approval can change depending on how busy Newcastle Council is, but on average, it takes 6-12 weeks.

 

3. Excavation & Steel Framework ( 1 -2 Weeks )

Once approvals are done, the pool area in your backyard is marked out and excavation begins. Heavy machinery shapes the area exactly as per the design.

After excavation, steel reinforcement is installed, forming a strong skeleton for the pool structure. This is one of the most critical steps because it determines the durability of the concrete in pool construction.

This stage takes around 1–2 weeks depending on access and soil conditions.

 

4. Concrete Shell Installation ( 1 Week )

The concrete shell is created using either shotcrete or formwork techniques. Skilled concrete pool specialists ensure thickness, strength and smooth finish.

After spraying and shaping the concrete, the shell is left to cure. Putting down concrete only takes a day, but it can take up to 4 weeks to cure. During that time, work can still be done around the pool.

 

5. Plumbing, Electrical & Finishes ( 2 - 4 Weeks )

In this step, special features like lighting, heating, drainage, filtration systems, and more are installed.

Interior finishes like tiling, pebblecrete, coping and surrounding landscaping are then added to complete the look.

This process usually takes two to four weeks, but it depends on how complicated the design is and what finishes are chosen.

 

6. Final Inspection, Cleaning & Handover ( 1 Week )

Your pool is thoroughly inspected, cleaned, filled with water and tested. When everything is safe enough for Australia, the pool makers let you go for your first swim.

 

Total Time to Install a Concrete Pool in Newcastle, New South Wales

On average, the complete installation takes 10–16 weeks from start to finish.

Whether you’re in Merewether, Mayfield, Wallsend, Charlestown, Kotara, or Lambton, the timeline remains similar depending on site conditions, design choices and council approval speed.

A concrete pool is a long-term investment — but the wait is absolutely worth it.